Aldi
Home > Projects & Clients > Aldi

Aldi

  • UK Headquarters, Atherstone, Warwickshire
  • Upgrade of existing power supply
  • Replaced existing 1000KVA cast resin transformer with 2000KVA transformer
  • Replaced clients incoming HV switchgear
  • Re-routed outgoing supplies from overloaded LV distribution panel onto new distribution panel
  • The works were all undertaken within an agreed 18 hour shutdown